The on-site engineer for the current Saddle Road improvement phase between m.m 11-19 e-mailed me this update on the project.
“Progress is moving along into the final segment of the project this week, meaning our earthwork operations will start from mm 13 to 11. We will also start paving after the first of the year down to mm 14. Once paving is completed to mm 14 we will start installing final striping and signs.”
Bolton Inc. started mobilizing equipment for the Holu Street Connector project today.
Bolton is slated to start work November 1st, 2010 on the Holu Street Connector project. They anticipate completing this roadway extension by the end of the year.
Senator Inouye‘s office finally responded (via postal mail) to my e-mails expressing concern about the availability of future funding for the Saddle Road project.
Lastly, AT&T submitted an application on October 28, 2010 urging the FCC to withdraw their recent Sandwich Isles Communications ruling.