Holu Street Connector Project Update

The on-site engineer for the current Saddle Road improvement phase between m.m 11-19 e-mailed me this update on the project.

“Progress is moving along into the final segment of the project this week, meaning our earthwork operations will start from mm 13 to 11. We will also start paving after the first of the year down to mm 14. Once paving is completed to mm 14 we will start installing final striping and signs.”

Bolton Inc. started mobilizing equipment for the Holu Street Connector project today.

Bolton is slated to start work November 1st, 2010 on the Holu Street Connector project. They anticipate completing this roadway extension by the end of the year.

Senator Inouye‘s office finally responded (via postal mail) to my e-mails expressing concern about the availability of future funding for the Saddle Road project.

Lastly, AT&T submitted an application on October 28, 2010 urging the FCC to withdraw their recent Sandwich Isles Communications ruling.

Advertisement

About Aaron Stene

I'm just a kama'aina, who is very concerned about the direction where the state of Hawaii is going. View all posts by Aaron Stene

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.

Join 465 other followers