The manager overseeing the Ane Keohokalole Highway project e-mailed me this update regarding upcoming construction work on Palani Road and Kamaka’eha Avenue.
“Schedule information for current and upcoming work:
Palani Rd – installation of new utility pole-line:
Start digging foundations – 1/24/11
Complete digging foundations – 2/18/11
Poles ship from West Coast – 2/21/11
Poles Arrive Hawaii – approx 3/16/11
Pole assembly and installation – 1 month
Wire Stringing (HELCO) – 1 week
HTCO and OTWC installation of new cables – approx 3 months
Approximate completion of pole-line installation – end of July 2011
Once this is complete, then the old wood poles can be removed and grading and paving operations can resume. These are expected to last 3 months. It is anticipated that there will be intermittent channelization of traffic throughout the paving portion of the work, and complete road closures at night on occasion during the pole installation and wire-stringing phases.
Kamakaeha Sewer line installation:
Phase-1: Makalapua end – 1/26/11 to 2/22/11
Two lanes closed between Macys and the movie theater driveways – traffic diversion through the shopping center. During this period, the public are asked to use Makala Blvd as primary access, and to minimize use of the diversion.

Phase-2: Macys driveway towards Palani Road- 2/23/11 to 3/23/11
Two lanes closed at Palani Rd and the Macy’s driveway, no through-traffic on Kamakaeha Ave. Access to Makalapua shopping center will be only from Makala Blvd (off Queen Kaahumanu Hwy).

During both phases of this work, there will be large construction equipment and dump trucks traveling on the roadway between the work site and a haul-road access at the top of Makala Blvd. Extreme caution is called for.
Yesterday we confirmed the scope of work required within the Henry Street Junction at Palani Rd. There are three 8′ to 9′ deep trenches required across Palani and one across the top of Henry Street. These are to be dug around and underneath two very large water transmission pipelines, and as such the trenching will be extremely technical and therefore slow.
There is unfortunately little we can do to minimize negative impacts on traffic through this busy intersection. We are currently planning and sequencing the work in this area, and I will let you know when we have a work schedule in place.”