Saddle Road Improvement Project Update

Road and Highway Builders LLC has made significant progress reconstructing Saddle Road (between m.m 11 and m.m 19). They’ve started excavation work by m.m 12. So, the completion of the earthwork portion of this project (by late March/early April 2011) is still on schedule. In addition, RHB is slated to resume paving on February 14th, 2011.

RHB still expects to complete this latest phase of the Saddle Road improvement project by the middle of 2011.

Advertisement

About Aaron Stene

I'm just a kama'aina, who is very concerned about the direction where the state of Hawaii is going. View all posts by Aaron Stene

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.

Join 465 other followers