Tag Archives: Puna Geothermal Venture

Hawaii PUC Approved PGV/HELCO New 8mW Power Purchase Agreement

Dave Gedeon, the CFLHD Saddle Road project manager, e-mailed me last weekend announcing his retirement. Mr. Gedeon’s e-mail caught me off guard. I didn’t expect he’d retire before the entire project was completed. Nevertheless, the CFLHD has replaced him and Bill Hakala, the CFLHD Saddle Road construction manager, with three new individuals. I hope they continue Mr. Gedeon’s sterling work as this project nears its completion.

Nan is preparing to pour two additional segments of cement (one up by the Henry Street intersection and another by the fire station). These new segments will connect the new concrete pavement to the existing Palani Road.

Hawaii County is soliciting bids to improve part of Kaiminani Drive. The county originally planned to resurface all of Kaiminani Drive, but they reduced the project’s scope later on. This was likely done because the mauka portion needed additional construction work.

I was irritated after reading this article over the weekend. I wish individuals, like Tim Terzi, would ask why these projects were delayed instead of grumbling to the newspaper about it.

“Shoulder work along Highway 180 heading to Holualoa where he said crews have been working in the same area for nearly two years;

Road improvements at the Kiholo Bay Scenic lookout on Queen Kaahumanu Highway, which he said have been going on for more than 18 months; and

The storage of rock at Ke Kahakai State Park rather than using it to smooth out the access road to Mahaiula beach.”

The Highway 180 roadway shoulder strengthening project has encountered several delays. There has been five project change orders thus far. However, Isemoto Contracting’s biggest challenge has been unforeseen subsurface/geotechnical issues.

Isemto was slated to finish this project by February 2012, but they’re probably going to seek a time extension to finish their work.

The pile of fill material by Kekaha Kai State Park will be used when construction begins on intersection improvements to this beach.

The Kiholo Bay lookout improvements project encountered one major delay, if I recall correctly. Sandwich Isles Communications had to relocate their fiber-optic cable, which resulted in a eight week delay. This project is slated to be completed by March 16, 2012.

Lastly, The Hawaii PUC approved PGV/HELCO’s new 8mW PPA on December 30th, 2011. Ormat expects to activate the new brine recovery facility, which will produce this additional electricity, sometime in January 2012.


Tawhiri Power LLC Filed A Motion To Intervene In The HELCO/PGV 8MW PPA Docket

The manager overseeing the Makalei Fire Station project e-mailed me this update:

“I just got some information from DPW that I thought I’d pass on just to keep you abreast of what’s happening as well as some other requirements that I hadn’t mentioned regarding the issuance of the NTP.

The contractor is now working on obtaining the permits (building, electrical, plumbing); grading;& permit to work in the State Right of Way. They’re also working on their materials and equipment submittals, sub-contractor agreements and construction schedule. Once those are in place, the NTP can then be issued. I didn’t get a timeline for those submittals but the contractor is working to get those permits and submittals done ASAP. “

Tawhiri Power LLC, owner of the Pakini Nui Wind Farm near South Point, recently filed a motion with the Hawaii PUC. They’ve requested to be a intervening party in the HELCO/PGV 8MW PPA docket. Tawhiri asserts this additional electricity is unneeded and may negatively impact their wind farm operation.

I hope Tawhiri Power’s concerns doesn’t  derail PGV’s expansions plans. Their new brine recovery facility could be put into operation later this year if they receive PUC approval by then.

New brine recovery facility

HELCO started installing the base of the new steel poles to be installed alongside Palani Road (between Henry Street and Queen Kaahumanu Highway) on Wednesday. I’m planning to get an update from the project engineer next week Wednesday regarding the upcoming work slated for this area.

Lastly, North Kona resorts were hit the hardest by the recent tsunami.


Saddle Road Improvement Project Remains On Track

Richard Ha blogged about the new HELCO/Puna Geothermal Venture 8MW power purchase agreement. This new generating capacity will be produced by reusing the brine byproduct of the existing steam generation process. Ormat Technologies is constructing this facility.

The deferral of the mayor’s 56 million dollar bond float left a sour taste in my mouth. I hoped the council would appropriate funding for several projects, such as the La’aloa Avenue Extension. However, the opponents of this bond float successfully torpedoed it. They claimed the funding was not tied to a specific project. Nevertheless, Big Island Video News posted part of Bill 311 which showed the list of projects allocated funding from this bond float.

I checked the county website to compare drafts of this legislation. The version posted on the county’s website doesn’t include the list of funded projects. So, I’ve officially inquired with county to see how many drafts of Bill 311 were created. I’ll certainly post an update if the county responds to my request.

I was absolutely thrilled after reading this article regarding the Saddle Road improvement project. The funding for the last two phases remains on track despite the loss of earmarks.

Related items:

Elimination Of Congressional Earmarks May Jeopardize The Completion of The Saddle Road Improvement Project

Saddle Road Improvement Project Breaking News


HI SR 200(3) and HI A-AD 6(2) Update

Lastly, I drove over Saddle Road on my way back to Kona last weekend. So, I was able to see the progress Road and Highway Builders has made reconstructing Saddle Road between m.m 11 and m.m 19.

RHB has excavated and graded most of the project (except on segment of old roadway near the bottom). They’ve also paved approximately 4 miles of new roadway.


La’aloa Avenue Extension Project Update

Richard Ha recently blogged about Puna Geothermal Venture‘s operational safeguards.  Big Island Weekly recently published an  article which raised questions about geothermal safety.

The new HELCO/PGV eight megawatt power purchase agreement may lower electricity costs for island consumers.

The cost of producing this additional eight megawatts won’t be tied to the price of oil. In addition, HELCO and PGV were able to hammer out a new five megawatt purchase  agreement. This replaces the old accord.

Oceanic Time Warner Cable has ceased offering Road Runner Turbo Plus (15Mbps/1Mbps) service for now.

A Oceanic customer service representative replied to my e-mail inquiry:

“The Turbo Plus listing has been removed for now. Customers who already have the service are able to continue to use the service, however we are not able to add new customers with this service at this time. Unfortunately we do not have details about why this change was made.”

Councilman Pete Hoffmann responded to my e-mail inquiring why the council hasn’t approved funding for the La’aloa Avenue extension project.

“Aaron,

We may see another bond float proposed by the Mayor which includes both projects. They have been properly added to the CIP, but don’t forget there’s no money in the CIP, it is only a ‘wish list’. The money to actually do the projects comes from bond floats, property taxes, state/federal grants, etc. I believe the Mayor will introduce another bond float that will handle at least these two projects and it will be done ‘properly’ this time.”

Lastly, the proposed Waimea Bypass (between mud lane and Waimea Airport) remains a paper road. The biggest issue is with the DHHL homesteaders. They remain vehemently opposed to the construction of this roadway.

I wish these homesteaders would see the bigger picture. This bypass road will benefit them and the entire community.


Puna Geothermal Venture And HELCO Officially Signed A New Eight Megawatt Power Purchase Agreement

Puna Geothermal Venture and HELCO made a significant announcement today. Both parties have officially signed a new 8 megawatt power purchase agreement. The new generating capacity will be produced by reusing the brine byproduct of the existing steam generation process. Ormat Technologies is constructing this new facility.

The State LUC posted the minutes from their January 20-21 meetings. They reverted The Villages at Aina Le’a's land use classification back to agriculture at their January 20th meeting.

I’m very interested to see what happens next. The developers have seven days after the release of the final D&O to petition the LUC to reconsider their decision. In addition, they could invalidate this land use reversion through the courts (within 30 days of the release of the final D&O).

The ongoing Saddle Road improvement project recently received a prestigious FHWA award for highway design. This award is a huge achievement for everyone involved in this project. They’ve successfully reconstructed/re-aligned a narrow roadway to modern standards.

The completion of these improvements may have hit a brick wall . Senator Inouye was able to secure 150 million dollars to upgrade Saddle Road thus far. Nevertheless, the current fiscally conservative climate will likely delay improvements to the last Hilo and Kona phases for the foreseeable future.

Lastly, Hawaiian Telcom filed an amended cable tv franchise application for the island of Oahu on November 10, 2010. I’m very skeptical of HawTel’s ability to reliably provide NGTV. Their aging last mile infrastructure will be their Achilles’ heal.


Puna Geothermal Venture Addresses Concern About Chemicals Used To Keep Pipes Corrision Free

Mike Kaleikini, Puna Geothermal Venture’s Plant Manager responded to this comment inquiring what chemicals PGV uses. He e-mailed me a list of chemicals (here, here, and here) they use  to prevent pipe corrosion.

“Aaron,

The majority of these are corrosion inhibitors. Over time, we’ve used several different vendors. So rather than be limited to only one or two vendors, we submitted the different chemicals from the different vendors in the event we switch vendors.

All chemicals are reviewed in great detail by the EPA and the State DOH.

These chemicals are standard in the geothermal industry. A lot are also used in conventional applications too.

Regards,

Mike”


Follow

Get every new post delivered to your Inbox.

Join 465 other followers