Tag Archives: Road and Highway Builders LLC

Saddle Road Improvement Project Update

The temporary orange barricades between m.m 29 and m.m 30.1 on Saddle Road is being replaced with permanent fencing. In addition, the shoulders were recently widened in this area. The CFLHD/HDOT did these improvements to prevent Nene from crossing the road or congregating by the shoulders.

Road and Highway Builders LLC did not install a Nene crossing between m.m 11 and m.m 19, according the CFLHD. I drove over this segment in late December and couldn’t find this crossing.

Lastly, Kirkland Construction is confident they’ll finish the earthwork phase of the last Kona side Saddle Road segment by December 2012, according to the HDOT’s Chief of Communications Dan Meisenzahl. I will believe this when I see it. The terrain in this area is probably nothing like Kirkland has faced before, so it will take a miracle if they finish six months ahead of schedule.


Saddle Road Improvement Project Update

Road and Highway Builders LLC‘s ongoing Saddle Road reconstruction project (between m.m 11 and m.m 19) is going well. They’ve made a lot of progress since January. RHB has paved almost 6 miles of new roadway despite weather and asphalt supply issues.


Saddle Road Improvement Project Update

Road and Highway Builders LLC has made significant progress reconstructing Saddle Road (between m.m 11 and m.m 19). They’ve started excavation work by m.m 12. So, the completion of the earthwork portion of this project (by late March/early April 2011) is still on schedule. In addition, RHB is slated to resume paving on February 14th, 2011.

RHB still expects to complete this latest phase of the Saddle Road improvement project by the middle of 2011.


Saddle Road Reconstruction Update

My girlfriend took these videos of Road and Highway Builders LLC‘s ongoing reconstruction of Saddle Road between m.m 11 and m.m 19.

They’ve started to pave the first two miles of roadway. In addition, RHB has started excavation work by m.m 13.


Palamanui/University Of Hawaii MOU Should Be Finalized Within A Week

The MOU between Palamanui and the University of Hawaii should be finalized within a week. In addition, the University of Hawaii is slated to officially award Keauhou Kona Construction Corporation the contract to build the initial campus roadway infrastructure.

CTS Earthmoving Inc. is scheduled to start the Kamaka’eha Avenue sewer line project today. The contractor recommends using Makaala Blvd from Queen Kaahumanu Hwy as an alternate route until construction is complete in mid-November.

The project engineer also informed me that motorists are still speeding on Palani Road between the Henry Street/Palani Road and Queen Kaahumanu/Palani Road intersections. Please slow down in this construction area.

Road and Highway Builders LLC has started full scale paving a few weeks ago on Saddle Road. RHB also has nearly completed grading work to m.m 14. I’m planning to drive over Saddle Road next Saturday to check RHB’s progress.

The project engineer for the future Makalei Fire Station project sent me this update:

“We’re still working with the DPW engineers for the plans review and specs. I’m still awaiting the affidavits of publication from thenewspapers to forward to FEMA. That way FEMA will allow us access to the Federal grant that we received for the project.”

Margaret Wille has posted an update regarding her ongoing Lalamilo roadway easement reservation lawsuit.

Oceanic Time Warner Cable’s plans to increase the speed of their Road Runner cable modem service appears to be moving forward.

I found this Honolulu Advertiser article which stated this about this upcoming speed increase:

“More speed is on the way from Oceanic, which this year plans to roll out a service having a top connection speed of up to 20 megabits per second. In 2012, it is planning an upgrade to DOCSIS 3.0 technology that allows downloads of up to 100 or more megabits per second.”

In addition, Peter Kay interviewed Alan Pollock, VP of Marketing at Oceanic Timer Warner Cable. This speed increase also was mentioned during this interview.

However, I found this recent blog posting which raised questions about Oceanic’s plans.

Lastly, there is two aspects of Sandwich Isles Communications ongoing FCC petition that don’t make any sense to me. Firstly, I wonder why Deutche Bank loaned Sandwich Isles Communications 185 million dollars even though NECA had not approved SIC’s request for subsidies.In addition, Sandwich Isles had a debt service payment due on February 20th, 2010 on the latter loan used to construct the Paniolo Fiber-optic Network.

It is uncertain if they defaulted on that payment or not. Nonetheless, I figure the bank is likely getting anguish about SIC’s ability to pay off this loan. There is a very real possibly that Sandwich Isles may only receive 1.9 million dollars in subsidies instead of 15 million dollars. That possible decision will likely cause both Paniolo and Sandwich Isles to file for bankruptcy.


Hokulia Responds To Questions About A Subdivision Code Variance Application They Recently Submitted

Hokulia recently submitted a subdivision code variance application to Hawaii County.

(Mahalo to the anonymous tipster who sent this document to me)

Private roadways servicing six or more lots have to be built to agricultural standards. The latter obligates Hokulia to pave and fully improve the right of way. However, they want to keep the current roadway shoulder landscaping and grassed swales.

I was deeply concerned about this application. It appeared Hokulia was attempting to reduce the cost of completing the subdivision roadway infrastructure. So, I e-mailed John DeFries to get his perspective:

(Note:  I re-wrote in my own words what he submitted to me per his request)

1. The Hawaii County zoning code was amended after the project was initially zoned A-1a. These revisions mandated that the minimum Agriculture District zoning category be no less than five acres (section 25-5-74 of the zoning code amended 1996 and 1999). So, two new designations (RA-1a and FA-1a) were created include Agriculture District classified lands under 5 acres. This is why Hokulia’s variance application has designated the land as RA-1a, not A-1a

2. Hawaii County subdivision code requires privately owned roadways servicing six or more lots to be constructed to agricultural standards. However, the latter still requires the entire right of way be paved and fully improved.

Hokulia wants to maintain the current roadway shoulder landscaping and grassed swales in lieu of making further roadway improvements. This is why they submitted this application.

3. This proposed variance won’t apply to roadways  required to be constructed to county standards (i.e Haleki’i Street)

Hawaii County is still reviewing this variance application.

Road and Highway Builders LLC was unable to start full scale paving this week between m.m 11-19 on Saddle Road. I received this update from RHB today:

“We have some fine tuning to still do. We did another test today – should get results in a day or so. The dirt is a little better than MP16 but some of the excavations cuts are deep so they go a little slower. I will let you know on the new test results.”

The opening of the Parker Ranch Connector Road may take a bit longer. The Hawaii County Council has to approve a resolution accepting the public use of this roadway. However, Parker Ranch and Hawaii County haven’t completed all the paperwork yet. So, this legislation likely won’t be agendized for the next council meeting on September 21st.

The Makalei Fire station NEPA EA process is moving along. FEMA will likely make a FONSI declaration early next week. I’m absolutely thrilled by this decision. The next step (after the paperwork is processed) is putting this much-needed public safety project out to bid.

From the project manager:

“I just received a call from Donna Meyer at FEMA and she indicated that she hasn’t received any comments regarding the NEPA EA. She will be writing the FONSI Declaration and it should be completed early next week. It will then need to be routed for the appropriate signature from her headquarters.Once I get a copy of the signed declaration, we are required to publish the FONSI in the local newspapers. I will keep you informed when I receive the FONSI.”

I noticed two additional court filings for Keoki Kai’s lawsuit against Hawaii County.

The litigants in Margaret Wille’s Lalamilo roadway easement reservation lawsuit have submitted additional court filings.

Lastly, Hawaii County gave  Bolton Inc. the notice to proceed for the Holu Street Connector Road project yesterday. The clock starts on October 11, 2010. Bolton has 120 working days to complete this project.


Missing Holu Street roadway segment


I’m absolutely ecstatic about this significant milestone. This roadway will benefit  residents living in Kona Highlands, Wonderview, Coastview, and Palisades.

(Related item: Holu Street Connector Road History)


Follow

Get every new post delivered to your Inbox.

Join 465 other followers